The Dung Quat Refinery Project was an industrial port project with offshore structures such as navigational aids and dredging works. It also included extensive armoured revetment for coastal and facilities protection. The offshore SPM (Single Point Mooring) structure, sea outfalls and jetties required the use of extensive coastal and offshore engineering computations for wave forces and sediment transport.

  • Bulk liquid material handling installations
  • Catenary Anchor Leg Mooring (CALM) offloading buoy
  • One-kilometre-long multi-berth jetty supported on steel piles
  • Dredging
  • 1.2 kilometre-long breakwater
  • Coast protection revetment
  • Seawater intake and outfall

Rendel’s services included:

  • Project Management Consultancy (PMC) services
  • Design review
  • Construction supervision
  • Equipment commissioning
  • Contract management and administration

PROJECT DETAILS

Location:

Vietnam

Client: PetroVietnam
Date: 2004 – 2010, and 2017
Services: Lead maritime engineer, construction, supervision and design review